Notice to the general contractor within 20 daysof first furnishing. Notice is not required when contracting directly with the principal (prime contractor).
Step 2: Bond Claim
Notice to and must be received by the general contractor within 90 days from last furnishing
Step 3: Suit Against Bond
After 90 daysfrom last furnishing but within 1 yearof final settlement of the contract
Bond Bits
Contracts less than $100,000 are excluded from bond requirements.