If the land being improved is “Public” the owner is state or county or a city (municipality).
These projects are not subject to the mechanic’s lien laws they’re subject to state bond claim laws.
Public Projects
If the land being improved is “Private” the owner is an individual, partnership or corporation.
These projects are not subject to the state bond claim laws, they’re subject to mechanic’s lien laws.
Public Projects
If the land being improved is “Federal” the owner is the Federal Government. These projects are not subject to the state bond claim or mechanic’s lien laws, they’re subject to Federal Miller Act.