Arizona Public Time Frames


Step 1: Notice
  • Notice to the general contractor within 20 days of first furnishing. Notice is not required when contracting directly with the principal (prime contractor).
Step 2: Bond Claim
  • Notice to and must be received by the general contractor within 90 days from last furnishing
Step 3: Suit Against Bond
  • After 90 days from last furnishing but within 1 year of final settlement of the contract

Bond Bits


  • Contracts less than $100,000 are excluded from bond requirements.
  • Amount of Bond: 100% of the contract price.