Florida Public Time Frames


Step 1: Notice
  • Notify prime contractor within 45 days of first furnishing or fabricating.
    • Except for laborers, notice is not required when contracting with the prime contractor (principal).

Step 2: Sworn Notice of Non-payment/Bond Claim
  • Notice of Non-Payment is a Sworn Statement under oath and must be served on parties by the 90th day of last furnishing.
  • Allow ample time for service by the 90th day

 

Step 3: Suit
  • Within 1 year from last furnishing.

Bond Bits

  • Amount of Bond: 100% of contract price.
  • Contracts less than $100,000 are excluded from bond requirements for state projects, $200,000 for county and city projects.
  • P3 Payment bonds are required per FS 287.05712 – notice and filing timeframes follow public statute.