Guam Private Time Frames
Home
Guam Private Time Frames
Guam
Statute
Law Link
Guam Private Time Frames
Guam Public Time Frames
Guam Speed Bumps
Guam Waivers
Construction
Credit Academy -
informative webinars
Submit
Service Request
Got Questions
Guam Private Time Frames
Step 1: Notice
Serve notice to the owner and prime contractor
within 20 days
of first furnished labor, service, equipment or materials to the job.
A late notice may be served but will only be effective for furnishing within 20 days of the notice.
Step 2: Lien
Not before last furnishing, but
within 90 days
of last furnishing. See
Speed Bumps
for potential shorting of lien timeframes.
Step 3: Foreclosure
Within
90 Days
of recording lien.