HOME
STATES
QUICK LINKS
Project Type Who is the Owner
Quick References
State Requirements at-a-Glance
Construction Credit Academy
Date Calculator
Enews
Glossary
REQUEST SERVICES
Notice, Lien, Bond & Waiver Filings
UCC – 1 Filing
CONTACT US
NACM
Contact us
Michigan Private Time Frames
Home
Michigan Private Time Frames
Michigan
Statute
Law Link
Michigan Private Time Frames
Michigan Public Time Frames
Michigan Oil & Gas Lien
Michigan Speed Bumps
Michigan Waivers
Public Records
Michigan County Resources
Michigan Private Time Frames
Step 1: Notice
Request Copy of Notice of Commencement.
Notice to the owner and to general contractor within
20 days
of first furnishing,
30 days
for laborers (full price lien).
Late notice - protects unpaid funds between owner and general contractor at time served.
Step 2: Lien
Within
90 days
of last furnishing labor or material. Serve on owner within
15 days
of filing.
Step 3: Foreclosure
Within
1 year
of filing lien.