Serve notice on the principal contractor within 30 days of first furnishing.
Step 2: Bond Claim
Serve written notice, on the principal contractor and governmental unit within 90 days from last furnishing.
Highway Projects: In addition a subcontractor or supplier must give notice via certified mail, return receipt requested, to the board of officers or agents contracting on behalf of the state (usually the Michigan Department of Transportation) in duplicate, within 60 daysafter the claimant last furnished its labor or material
Step 3: Suit Against Bond
Non-Highway: After90 days, but within 1 year, of final payment to the general contract.
Highway Projects: Any time within 1 year after completion and acceptance of the project.
Bond Bits
Contracts less then $50,000 are excluded from bond requirements.
Amount of Bond: Not less than 25% of the contract price.