Nebraska Public Time Frames
Step 1: Bond Claim
Notice to the contractor within
4 months
of last furnishing.
Step 2: Suit Against Bond
Within
1 year
after the date of final statement of the principal contract.
Bond Bits
Contracts less then $15,000 (state projects), $5,000 (others) are excluded from bond requirements.
Amount of Bond: 100% of contract price.