Nevada Private Time Frames


Step 1: Notice
  • With the exception of laborers: Serve owner and prime contractor within 31 days of first furnishing. See Speed Bumps for multi-family or single family residence time frames.

Step 2: Lien
  • Multi-family or single family residence, including apartment buildings: Serve 15-day Notice of Intent to Lien prior recording a lien. See Speed Bumps.
  • Commercial: within 90 days after the date on which the latest of the following occurs:
  1. Completion of project improvement
  2. Last delivery of material or work
  • Notice of Completion being recorded by owner: File lien within 40 days of the recordin
  • Serve lien on owner within 30 days of recording lien.
 
Step 3: Foreclosure
  • After 30 days but within 6 months after the lien is recorded, unless an “extension agreement” extending the period to 1 year is recorded.