Vermont Speed Bumps


Private Speed Bumps

  • Vermont is an UNPAID BALANCE lien state.
  • Protection afforded under Vermont’s lien law statute is extremely broad and covers virtually all parties that perform labor or furnish materials on a project to generally include suppliers to suppliers.

Mechanic’s Lien Speed Bumps

  • The time limits for filing a Claim of Lien in Vermont begins from the date when payment became due for the last of labor performed or materials furnished.
  • Notice of the intent to claim a lien must be given by materialmen or laborers to the owner or his agent that they will claim a lien for materials to be furnished or labor to be performed. Such notice must also be filed with the clerk of the town in which the relevant real estate is situated within 180 days of the due date of the final payment. "Vermont law does not use the last day of work or furnishing of materials to begin the lien process," according to NACM's Manual of Credit and Commercial Laws. "The time limitation for filing a claim of lien in Vermont begins to run from the date when payment became due for the last of labor performed or materials furnished."

Foreclosure Speed Bumps

  • In addition to filing a civil action complaint to enforce the lien within 180 days of the filing of the notice of mechanic's lien, claimants must also obtain and record a prejudgment writ of attachment of the real estate during the same 180-day period in order to effectively foreclose on the lien. One action is useless without the other.
  • Once a hearing is set, it is the plaintiff’s (lien claimant’s) responsibility to provide the owner with a Notice of Hearing on the Writ of Attachment.
  • Liens do not take precedence over mortgages recorded prior to the recording of Notice of Mechanic’s Lien.
  • Attorney fees are not included in the amount of the lien, but prejudgment interest may be awarded in the court’s discretion.

Public Speed Bumps

  • Vermont provides no specific provisions for protection on public construction contracts, except for highways. Thus if a surety bond is provided, the terms of the bond itself control. There is, however, a requirement that the general contractor cannot receive the final payment until it files a sworn statement that all labor and material claims have been paid and designating where disputes exist. The disputed amount is then withheld until the dispute is determined.
  • Performance and payment bonds apply to transportation projects only. Amount of performance and payment bonds to be determined by transportation agency.