- Residential: Serve within 75 days of last furnishing.
 
						- Commercial:
							
								- Serve Notice of intent to lien: (Notice of intent not required when contracting direct with property owner)
									
										- Within 75 days of last furnishing material, labor or services  for claims less than $1,000.
 
										- Within 120 days of last furnishing material, labor or services  for claims more than $1,000 after last furnishing.
 
									 
								 
								- File Lien within 6 months from last furnishing. Serve copy of statement of lien on the owner within 7 days after the statement is filed.
 
							 
						 
					 
				 |